Engine
11 - Dry Dock Systems
Final integration of shore utilities and optimization of vessel systems for dry dock operations including shore power stabilisation and utility connections.
Shore Power System Verification
| # | Action | Status | |
|---|---|---|---|
| 1 | Shore Power Converter Cooling System | RUNNING | |
| 2 | One Air Conditioning Unit | RUNNING | |
| 3 | Shore Power Supply | STABLE | |
| 4 | Emergency Generator Automatic Mode | OFF |
System Optimization for Dry Dock
| # | Action | Status | |
|---|---|---|---|
| 5 | Non-Essential Consumer Breakers | OFF | |
| 6 | Chilled Water Isolation Valves | CLOSED | |
| 7 | All Non-Required Breakers | OFF | |
| 8 | Electrical Consumers at Minimum | SET |
Shore Utility Connections
| # | Action | Status | |
|---|---|---|---|
| 9 | Fire Fighting Shore Water Hose | CONNECTED | |
| 10 | Wastewater Valve to Shore Discharge | SET | |
| 11 | Shore Wastewater Discharge Hose | CONNECTED | |
| 12 | Fresh Water Bunkering Hose | CONNECTED |
Documentation and Monitoring
| # | Action | Status | |
|---|---|---|---|
| 13 | Water and Electricity Meter Readings | LOGGED | |
| 14 | Dry Dock Systems Integration | LOGGED |
Dry Dock Entry
Comprehensive preparation for dry dock entry including pre-operation verification, critical systems shutdown, and power transition from main generators to emergency power.
Undocking
Complete systematic vessel launch procedure ensuring all machinery, safety systems, and sea connections are properly configured for safe water entry and initial operations. This checklist covers pre-launch preparations through post-launch verification.